- 1. Introduction
1.1. Purpose
The Mission Plan for Mars Global Surveyor (MGS) describes a baseline strategy for achieving the scientific objectives of the mission within the capabilities and constraints of the project systems, subject to the project policies on the use of these systems. This strategy will serve as a starting point for planning detailed event sequences, both before launch and during the mission. The Mission Plan also serves as the basic reference for a detailed description of the mission. It documents the major design features and options considered by the Project along with the rationale for major technical decisions.
1.2. Scope
This document responds to the high-level project policy and requirements documents. Accordingly, the Mission Plan does not originate new mission and system requirements. It describes a strategy for conducting the baseline mission which is consistent with the requirements, capabilities, and constraints defined in other project documentation. The baseline mission is the planned series of mission events that barring failure, normally proceed from launch to the end of the mission.
Section 2 Overview of Spacecraft Design, Science Instruments, and Baseline Mission Section 3 Description of Launch Phase Section 4 Description of Cruise Phase Section 5 Description of Orbit Insertion Phase Section 6 Description of Mapping PhaseDisclaimer
The current version of the Mission Plan (this document) represents a draft of the final version of the Mission Plan, due for release at the Mission System critical design review in September 1995. As such, this Mission Plan release is for review only. All information presented represents the most current data as of 30 June 1995. Many issues in the design, particularly in the orbit insertion phase, have yet to be resolved. Consequently, the information is subject to change between now and the Mission System critical design review.
Several appendices that contain more detail pertinent to various technical issues in the Mission Plan will be supplied with the final version. In addition, an appendix addressing compliance of the mission with the Mission Requirements Document will also be supplied.
1.3. Relationship to Other Documents
The Mission Plan is consistent with and responsive to the requirements and objectives of the following project documents:
Mars Global Surveyor Project Plan (542-100) Investigation Description and Science Requirements Document (542-30) Mission Requirements Document (542-400) Planetary Protection Policy NASA NHB 80201.12BBased on the best information available as of 30 June 1995, the Mission Plan is consistent with the capabilities and constraints of the project systems as described in the following documents:
Spacecraft Requirements (542-200) Mission Operations Specification (542-409) Payload Policy and Requirements (542-40) Navigation Plan (542-406) Planetary Protection Plan (542-402)Some more detailed aspects of the mission design for Mars Global Surveyor are described in the following documents:
Trajectory Characteristics Document (542-410) Delta 2 Target Specification (542-411) Planetary Constants and Models (542-415) Performance Assessment Report (542-408) Mission Sequence Plan (542-407) Detailed Mission Requirements (542-424)
1.4. Update Schedule
Updates for the Mission Plan will occur on the following schedule as set by the MGS Mission Manager:
Draft Version August 1994 Preliminary September 1994 Draft for Final June 1995 Final September 1995 Update to Final July 1996
1.5. Acknowledgments
The authors of the mission plan are extremely grateful to the following members of the MGS team who provided information and inputs critical to the writing of the plan:
Joe Beerer, Dan Johnston, Dan Lyons Mission Design (JPL) Stan Butman, George Chen, Charles Whetsel Spacecraft & Subsystems (JPL) Gene Bollman, Pat Espositio Navigation (JPL) Nick Smith, Jim Taylor Mission Design (Lockheed-Martin)
1.6. Questions or Comments?
General comments, corrections, suggestions, or inquires about this document may be submitted to the authors:
Wayne Sidney Wayne Lee Jet Propulsion Laboratory Jet Propulsion Laboratory Mail Stop 264-235 Mail Stop 301-180 4800 Oak Grove Drive 4800 Oak Grove Drive Pasadena, CA 91109 Pasadena, CA 91109 (818) 393-1281 (818) 354-8784 Wayne.P.Sidney@ccmail.jpl.nasa.gov wayne@cranberry.jpl.nasa.gov