Mars Observer and Mars Global Surveyor
Mars Global Surveyor is the name given to a small orbiter, to be launched in November 1996, that will recover some of the science goals of the lost Mars Observer mission.
MGS will be roughly half the mass and size of Mars Observer. The image above shows both spacecraft in their mapping configurations. (It was rendered at MSSS from our own preliminary models and is not "official".)
Press Releases
- February 1994 Mission Announcement
- July 1994 Spacecraft Manufacturer Selection
- July 1994 Discussion of Innovations Associated with Mars Global Surveyor
- July 1994 Description of Basic Mission
Instrument Selection
The instruments selected for Mars Global Surveyor are the Mars Orbital [previously, Observer] Camera (MSSS/Caltech), the Thermal Emission Spectrometer (Arizona State University/Hughes Santa Barbara Research Center), the Mars Orbiter [previously, Observer] Laser Altimeter (NASA Goddard Space Flight Center), the Magnetometer/Electron Reflectometer (GSFC), and the Mars Relay [previously, Mars Balloon Relay] (French National Center for Space Exploration, CNES). Radio science will also be done, via an Ultrastable Oscillator in the spacecraft's downlink subsystem.The other two instruments on Mars Observer, the Gamma Ray Spectrometer (UofA/MMAG) and the Pressure-Modulator Infrared Radiometer (JPL), will be flown on a small orbiter to be launched in 1998.
Mars Orbital Camera
The Mars Orbital Camera (Mars Global Surveyor Orbiter Camera), or MOC 2, is the spare instrument fabricated during the Mars Observer mission. The investigation's science objectives, hardware implementation, ground data system, and science analysis plans are essentially identical to those of the Mars Observer investigation. These are described in a series of papers published prior to the loss of Mars Observer.Additional materials available include:
Some pictures of the MOC 2 electronics prior to their integration with the optics
Reports on progress towards integrating, testing, delivering, and further testing of the MOC 2
Spacecraft Selection
The Request For Proposals for the spacecraft was issued in early April, and responses were received in mid-May. On 8 July, JPL announced that Martin Marietta Technologies Inc. of Denver, Colorado, had been selected to build Mars Global Surveyor.
MGS Project WWW Server
Mars Global Surveyor Project server at JPLMGS Timetable
-
3 to 24 Nov 1996
- Launch on Delta II 7925
- 10 to 27 Sep 1997
- Mars Orbit Insertion into capture orbit
-
Oct 1997 to Jan 1998
- aerobraking to 380-km circular mapping orbit
- late Jan 1998
- Mapping mission starts
Preliminary version of the MGS Mission Plan
Return to MSSS Home Page